Submit R-O-W drawing to the relations section in the concerned operating area.
¾ The actual construction work shall not be started until the digging permit from relevant
authorities is obtained.
Standard R-O-W locations for underground utilities in streets of new areas have been
developed by the Ministry of Municipal and Rural Affairs in coordination with the Ministry
of Communications and the ministries having authority over the concerned utilities.
Warranty: 365 days Goods status: new/used Shipping method: Courier delivery
About us
We are professional company and we are expert in this business, we have highly experienced production team, or sales team, or purchase team, we have most advanced production line. We are reputable in the market.
Trench Excavation
Before proceeding with actual work of trench excavation,
following preparations should be completed:
• Review the cable route drawings, R-O-W drawings, digging permit, and inspect the cable route from end to end.
• Decide locating where cable drums shall be unloaded at site, keeping in view the actual cable lengths on drums.
• Decide locations of cable joints. Avoid street intersections. Joints should preferably be made not closer than 10 meters from edge of any street intersections.